WestConnex Stage 3B – Rozelle Gantry
Description: Initial preparation of the Rozelle Interchange required the fabrication and installation of a gantry frame to support an elevated office complex structure. A total of 180 tonnes of steel was required to complete the project in four major erection stages.
Client: John Holland CPB JV
Contract Value: $990,000
Location: Rozelle Interchange, Lilyfield
Duration: Nov 2019 – Dec 2020